Finite Capacity Material Requirement Planning System for a Three-Stage Supply Chain Under Manufacturer-Managed Scheduling Concept

Finite Capacity Material Requirement Planning System for a Three-Stage Supply Chain Under Manufacturer-Managed Scheduling Concept

Benyaphorn Paopongchuang, Pisal Yenradee
Copyright: © 2023 |Pages: 28
DOI: 10.4018/IJKSS.323147
Article PDF Download
Open access articles are freely available for download

Abstract

Supply chain management (SCM) is critical to the success of manufacturing industries. Advanced production planning and scheduling functions capable of coping with activities in a supply chain (SC) are presently needed. A finite capacity material requirement planning (FCMRP) system for a three-stage SC, defined as “3-SC FCMRP,” is presented herein. The system aims to generate feasible production and transportation schedules for the SC based on the manufacturer-managed scheduling concept, which allows the main manufacturer to manage the production schedule by considering the finite capacities of the factory work centers, suppliers, as well as customers. The system is based on a modular design concept that allows each module to be modified easily and independently. Experimental results show that all subsystems have statistically significant effects on the total cost of the SC, and schedules generated by the 3-SC FCMRP system are more realistic than those generated by the FCMRP system for the single or two-stage SC.
Article Preview
Top

Introduction

Enterprise resource planning (ERP) is an integrated management software for key business processes (Mesbahi et al., 2015), and it is used widely in supply chain management (SCM) where practices can be implemented jointly among supply chain partners so that they will remain competitive in a fast-changing business environment (Aggestam, 2016; Fernando & Evans, 2015). ERP software generally uses traditional material requirement planning (MRP) technique introduced by Orlicky in 1975 which allows the calculation for its production and purchasing planning modules. Traditional MRP assumes that manufacturing lead times are fixed constants (not dependent on production quantities) and that production capacities of all work centers are infinitely available (Jazouli et al., 2021). A master production schedule (MPS) is a key input that drives MRP calculations. Production and purchasing schedules are obtained after the MRP calculations are completed; however, due to the assumptions mentioned above, the production schedule may turn out to be infeasible in terms of capacity (i.e., the required capacity is more than available capacity) (Kanet & Stoblein, 2010; Teo et al., 2011). In such a case, a planner must either revise the MPS or the capacity level of post-MRP stage manually until the capacity becomes feasible (Permana et al., 2021). In practice, these manual revisions are time-consuming and complicated, and it is possible that the planner may not be able to achieve feasible capacity. This makes the use of traditional MRP logic in most ERP software a major disadvantage.

Many research studies have attempted to solve this disadvantage of the traditional MRP logic by developing a more advanced MRP logic called Finite Capacity MRP or the FCMRP system (Hill et al., 1997; Kim & Van Oyen, 2000; Pandey et al., 2000; Sum & Hill, 1993; Taal & Wortmann, 1997). Most FCMRP systems available in the literature are based on two basic assumptions: (1) that manufacturing lead times are not a fixed constant but dependent on production quantities, and (2) that all key work centers have finite capacities; the capacity used must not be greater than the available capacity. However, when the MPS has many orders competing for work centers, some orders may be completed later than their due dates.

Many research studies have attempted to solve this disadvantage of the traditional MRP logic by developing a more advanced MRP logic called Finite Capacity MRP or the FCMRP system (Hill et al., 1997; Kim & Van Oyen, 2000; Pandey et al., 2000; Sum & Hill, 1993; Taal & Wortmann, 1997). Most FCMRP systems available in the literature are based on two basic assumptions: (1) that manufacturing lead times are not a fixed constant but dependent on production quantities, and (2) that all key work centers have finite capacities; the capacity used must not be greater than the available capacity. However, when the MPS has many orders competing for work centers, some orders may be completed later than their due dates.

Complete Article List

Search this Journal:
Reset
Volume 15: 1 Issue (2024)
Volume 14: 1 Issue (2023)
Volume 13: 4 Issues (2022): 2 Released, 2 Forthcoming
Volume 12: 4 Issues (2021)
Volume 11: 4 Issues (2020)
Volume 10: 4 Issues (2019)
Volume 9: 4 Issues (2018)
Volume 8: 4 Issues (2017)
Volume 7: 4 Issues (2016)
Volume 6: 4 Issues (2015)
Volume 5: 4 Issues (2014)
Volume 4: 4 Issues (2013)
Volume 3: 4 Issues (2012)
Volume 2: 4 Issues (2011)
Volume 1: 4 Issues (2010)
View Complete Journal Contents Listing